| To
construct any building, permission of VMC is
must by law. The approval of development plan
is given in accordance with GDCR. The processing
of large number of documents is required to
enable this corporation to deal in accordance
with rules. To avoid unnecessary delay corporation
is required with complete application along
with following documents. Incomplete applications
are to be rejected on receipt by Building Inspector
with reasons. After development plan approved,
you have to give an application to the corporation
to carry out site inspection when the construction
of building reaches the plinth level. Thereafter
also, the same procedure is to be carried out
when the complete building is constructed. At
both these stages, VMC will issue certificate.
The certificate of completion is pre requisite
for obtaining drainage and water connection.
You have to pay fee for plinth check at the
rate of Rs. __________ per sq. meter. |
| You have to apply in the prescribed
form of GDCR. |
| Requirements for Application
: |
| Following documents should be enclosed
with the application. |
| |
|
| 01. |
Certificate by licensed Architect of Vadodara
Municipal Corporation in form
2 A. |
| 02. |
Certificate by licensed structural Engineer
of Vadodara Municipal Corporation in form
2 B. |
| 03. |
Certificate by the site supervisor / clerk
of the works in form
2 C. |
| 04. |
Ownership proof |
| |
| (a) |
Copy of recent property
card |
| (b) |
TIPPAN of DILR |
| (c) |
Abstract of city survey of 7/12 |
| (d) |
Possession Certificate for area
and TP scheme with site plan, which
will be provided on payment of Rs.
100/- by the Vadodara Municipal Corporation
authority. |
|
| 05. |
For proposed TP scheme you have to procure
a certificate from CTPO. |
| 06. |
“No Objection Certificate”
from Airport authority if your proposed
property is within 900 square meter of the
Airport. |
| 07. |
“No Objection Certificate”
of the fire Department of Vadodara Municipal
Corporation if the height of your building
is above 15 meter. |
| 08. |
“No Objection Certificate”
of GEB if your property is in vicinity of
H.T. line. |
| 09. |
Certificate of Archeological Department
of Government of India if your property
is within 200 sq. meter of a protected monument
declared by the Archeological Department. |
| 10. |
Allotment letter of the society if property
is situated in a formed society. |
| 11. |
Where development is on agricultural land,
process of development plan will be taken
up on the condition that you have to procure
N.A. Certificate. |
| 12. |
Where multiple unit consumption is spread
over more than 1500 sq. meter in residential
development and in 5000 sq. meter in Industrial
unit, provision of common plot should be
shown and should be utilized for the prescribed
purposes as per GDCR. |
| 13. |
When revision plan is submitted earlier
approved plan should be produced along with
application. |
| 14. |
Photostat copy of receipt of the payment
made for incremental contribution. |
| 15. |
Three copies of plans for approval. |
| |
|
|
90 working
days from the date of receipt of application
complete in all respect. During this period
the surveyor of Vadodara Municipal Corporation
who will advise the applicant in advance of
the date and time of his visit will do site
visit. If any inconsistency in the proposal
and the provision of bylaws, summary of observations
will be furnished within 45 days of the date
of application. If applicant fails to comply
within 60 days of date of application, his application
will be rejected. |
1 year from
the date of issue. The same may be renewed for
the period of three years on payment of Rs.
__________. Thereafter the permission granted
lapsed. |
The Town Planning
department will communicate final order on the
application; if such communication is not received
within seven days after the processing period
is over, the applicant may approach the Town
Development officer (Building Permission). |
| Completion Certificate and
Occupancy Certificate : |
Will be given after the applicant obtains
No Objection Certificate form drainage and
water department.
At the stage of plinth check
applicant has to give simple application on
plane paper locating the address and citing
building permission certificate number. Works
that invade alteration and / or construction
limited to the first floor of the house, the
application should be floated to concerned ward
office along with above information. |
Services
offered by the Building Permission Department
|
All records
to the concerned applicants on payment of fees
in the record department of Vadodara Municipal
Corporation. |